METHODOLOGY FOR CONCRETE KERB

METHODOLOGY FOR CONCRETE KERB
(Acceptance criteria: Ref. Sec 408 of MORT&H)

Scope:

This work shall consist of construction of cement concrete kerb and kerbs with channel in the central median and/or along the footpaths or separators in conformity with the lines, levels and dimensions as specified in the drawings.

Equipment/Machinery Requirement:

  1. Batching Plant
  2. Transit Mixer
  3. Kerb Casting Machine (Continuous)
  4. Concrete Cutting Machine

Procedure:

  1. Surveyor will give line, Level and Layout, before starting the job.
  2. Sensor rope will be fixed as per level/line.
  3. Concrete of M-20 grade will be used. Slump at site will be maintained between 10-15mm.
  4. Concrete Kerb will be provided with grooves (vertical cut) at 5m intervals with the help of concrete cutter, prior to hardening.
  5. Curing of concrete Kerb will be done as required.
  6. Casting of cubes will be done at batching plant as per requirement.